| Subcontracting Rates (ticpr1160m000) Use this session to list and define subcontracting rates by price-calculation code, subcontractor, and task. If you
enter an item in the Parent item field, you can define item-specific
rates. Subcontracting rates are rates for subcontracted operations, and are
used to calculate subcontracting operation costs. Performance aspects The settings in this session could affect system performance and database growth. For more information, refer to Cost component setup Project A collection of manufacturing and purchasing actions that are
performed especially for a particular customer order. A project is initiated by
a customer order for items having a To Order order policy. The purpose of a project is to plan and coordinate the production
of these items. For a standard-to-order production, the project is only
used to link the item with the customer order. Otherwise, a project can
include: - Customized item data (BOMs and routings)
- Project planning (activity planning)
A budget is a special type of project. A budget is used to
plan and estimate, not to carry out production. Price Calc. Code A specification of how a cost price, valuation price, or sales
price is calculated. The code stores specific cost calculation data. The price calculation code that is defined in the Cost Price
Calculation (CPR) Parameters determines the standard cost price. Other price
calculation codes are used for simulation purposes. The price calculation code
for customized items is stored by project. Example - Specific operation rates
- Subcontracting rates
- Simulated purchase prices
- Surcharges
Parent item The end item on the production order for which one or more operations can be
subcontracted. Subcontracting with Material Flow If this check box is selected, subcontracting with material
flow applies. Subcontractor Independent If this check box is selected, the specified rates are used to calculate
operation costs for the subcontractor-independent operations and functions as
fall back rates in case the subcontractor is known, but no rates are specified
for that subcontractor. Note The subcontracted tasks needed for the production of the end
item are not yet linked to a subcontractor, but the way subcontracting rates are calculated remains the
same. Subcontractor A business partner that is hired to perform certain services,
such as the execution of a part of a project or production order. The services
are delivered via a purchase order. Task The task to which the
subcontracting rate is linked. Calculation Method for Subcontracting Costs Cost Component The cost component must be of
the Operation Costs type. This is the cost component on which the estimated
subcontracting costs can be viewed in the cost-price calculations and
production order costing. Subassembly If this check box is selected, the component is used as a
subassembly. If you are subcontracting with material
flow, you can optionally enter the item that is the result of a subcontracted
operation. This item becomes the default value of the Subassembly field in the Routing Operations (tirou1102m000) session. If you are subcontracting without material flow, you must enter an item of the Subcontracted Service type, defined in the Items - General (tcibd0501m000) details session. This item represents the subcontracted
operations, and appears on the subcontracting purchase order. Subc. Rate Multi Curr. The subcontracting rate if you use an independent currency
system. The currency that is
displayed as default, and the corresponding subcontracting rate are related to
the currency system. The default currency is used in internal calculations. The
other currency relates to the currency of the supplier and can be manually
entered. This currency is used when generating a purchase order. Currency The default currency and the corresponding subcontracting rate
are related to the currency system that is used in internal calculations. This
currency relates to the currency of the supplier and can be entered manually.
This last one is used on generation of the purchase order. | |