If this check box is selected, the session uses the bill of material (BOM) that is valid on
the date that you specify.
If this check box is cleared, the session uses the current date.
Check Phantoms for Planning (tibom1220m000)Use this session to check and optionally correct the order system of a range of items. This check prevents particular types of error in which Enterprise Planning plans only a part of the items in an item structure or fails to transfer planned production orders to the execution level because of missing operations.
Check Effectivity against Date If this check box is selected, the session uses the bill of material (BOM) that is valid on
the date that you specify. If this check box is cleared, the session uses the current date. Check Effectivity against Date LN checks the item structure and the order system based on the bill of material (BOM) that is valid on
this date. Simulate Only If this check box is selected, LN does not change the order systems of any item, but only generates
a report.
Process Starts processing.
| |||