Assembly Order - WIP Estimates (tiasc7500m000)

Use this session to display WIP estimates for assembly orders.

WIP estimates are the estimated costs per order, per line.

The estimated WIP is based on the order content as it is on the moment the order is frozen.

The costs can be split up in cost components.

 

Assembly Order
Assembly Line
A set of consecutive line stations in which FAS (Final Assembly Schedule) items are manufactured. The items are manufactured by passing the items from line station to line station and by carrying out operations at each line station. An assembly line is subdivided into a number of line segments separated by buffers. An assembly line can be either a main line or a supplying line.
Calculation Date
When the WIP estimates were calculated.
Cost Component
A cost component is a user-defined category for the classification of costs.

Cost components have the following functions:

  • To break down an item's cost price, sales price, or valuation price.
  • To create a comparison between the estimated production order costs and the actual production order costs.
  • To calculate production variances.
  • To view the distribution of your costs over the various cost components in the Cost Accounting module.

Cost components can be of the following cost types:

  • Material Costs
  • Operation Costs
  • Surcharge on Material Costs
  • Surcharge on Operation Costs
  • WIP Transfer Costs
  • General Costs
Note

If you use Assembly Control (ASC), you cannot use cost components of the General Costs type.

Amount
The size of the cost component.