Approve Pick-up Sheets (tdsls3211m200)

Use this session to approve pick-up sheets.

In addition, you can use this session to specify options for consolidating sales schedule lines (pick-up sheet lines) on planned warehouse orders.

Note

To consolidate pick-up sheet lines after approval, use the Consolidate Planned Warehouse Orders (Pick-up Sheets) (tdsls3220m100) session.

 

Simulate Approval
If this check box is selected, pick-up sheet approval is only simulated, not processed.

If this check box is selected, the following are shown:

  • The effects of the pick-up sheet approval. This enables you to understand the changes and to, for example, manually intervene or not approve this pick-up sheet and wait for the next (changed) pick-up sheet.
  • For each line of the pick-up sheet, updates to linked planned warehouse orders. The creation of new planned warehouse orders for new lines is not reported.
Note
Print Errors
If this check box is selected, if errors occur during the approval process, an error report is printed.
Consolidate Options for Planned Warehouse Orders
Ignore Delivery Pattern
If this check box is selected, the Delivery Pattern, as specified in the Sales Contract Line Logistic Data (tdsls3102m000) session, is ignored when consolidating sales schedule lines on planned warehouse orders.
Move Past Requirements
If this check box is selected, for schedule lines with a requirement start date in the past, the New Requirement Start Date is used when consolidating sales schedule lines on planned warehouse orders.
Note

You cannot select this check box if the New Requirement Start Date is in the range of Original Requirement Start Date From and Original Requirement Start Date To and the Combine Planned Warehouse Orders check box is also selected.

New Requirement Start Date
The new requirement start date used to consolidate schedule lines with a requirement start date in the past.
Move Nonpattern Requirements
If this check box is selected, for schedule lines with a requirement start date not derived from the Delivery Pattern, the New Requirement Start Date is used when consolidating sales schedule lines on planned warehouse orders.
Note

You cannot select this check box if the New Requirement Start Date is in the range of Original Requirement Start Date From and Original Requirement Start Date To and the Combine Planned Warehouse Orders check box is also selected.

New Requirement Start Date
The new requirement start date used to consolidate schedule lines with a requirement start date not derived from the Delivery Pattern.
Combine Planned Warehouse Orders
If this check box is selected, for schedule lines with a requirement start date that is in the range of Original Requirement Start Date From and Original Requirement Start Date To, the New Requirement Start Date is used when consolidating sales schedule lines on planned warehouse orders.
Note

You cannot select his check box if the new requirement start date of one of the other options is in the range of Original Requirement Start Date From and Original Requirement Start Date To.

New Requirement Start Date
The new requirement start date used to consolidate schedule lines with a requirement start date that is in the range of Original Requirement Start Date From and Original Requirement Start Date To.
Original Requirement Start Date From
The first date in the range of original requirement start dates that must be changed for consolidation.
Original Requirement Start Date To
The last date in the range of original requirement start dates that must be changed for consolidation.

 

Approve
Approves the pick-up sheets in the selection range.