Vendor Rating Objective Scoring Scheme (tdpur8195m000)

Use this session to maintain and to display objective scoring schemes.

You can use an objective scoring scheme to assign scoring values to an objective criterion and to assign rating percentages to the scoring values.

Example

You can assign an objective scoring scheme to items and to business partners in the following ways:

  • If you leave the Item field and the Business Partner field blank, the objective scoring scheme applies to all items.
  • If you only fill the Item field, the objective scoring scheme applies only to the specified item.
  • If you only fill the Business Partner field, the objective scoring scheme applies only to the items that the specified business partner delivers.
  • If you fill both the Business Partner field and the Item field, the objective scoring scheme only applies to the specific business partner or the item combination.
Note

LN searches for an objective scoring scheme, which is used to convert scoring values into rating percentages, in the following sequence:

  1. LN searches for an objective scoring scheme for the business partner or the item combination.
  2. If no scheme is present for the business partner/item combination, LN searches for an objective scoring scheme for the business partner.
  3. If no scheme is present for the business partner, LN searches for an objective scheme for the item.
  4. If no scheme is present for the item, LN applies the default objective scoring scheme of the objective criterion.

 

Criterion Type
The objective criterion type to which this scheme applies.

Allowed values

  • Delivery
  • Quality
  • Quantity
  • Cost Performance
  • Order Confirmation
Business Partner
The business partner for which the objective scoring scheme applies.

Allowed values

You can only enter business partners of these types:

Item
The item to which the objective scoring scheme applies.
Unit
The time unit that is used if the criterion type is Delivery or Order Confirmation.

For the other criterion types, this field reads Not Applicable.

Value
Specify the scoring values in the scoring scheme, which are compared to the automatically calculated objective values for the criterion type.
  • Delivery
    If the value is positive, this is the number of days or hours the goods are delivered too late. If the value is negative, this is the number of days/hours the goods are delivered too early.
  • Quality
    The ratio of the approved quantity and the received quantity.
  • Quantity
    The ratio of the received items and the ordered items.
  • Cost Performance
    The ratio of the invoiced price and the purchase price.
  • Order Confirmation
    The number of days or hours between order entry and order confirmation.

Example

  • Criterion type: Delivery
  • Unit: Days
ValuePercentageValues for which the percentage applies
-510%< -5
-150%-4 - -1
0100%0
540%1 - 5
10030%6 - 100

 

If the delivery of the items is three days early, the rating that is assigned to the delivery is 50%.

If the delivery is four days late, the rating assigned to the delivery is 40%.

Percentage
Assign rating percentages to the scoring values.

Example

  • Criterion type: Delivery
  • Unit: Days
ValuePercentageValues for which the percentage applies
-510%< -5
-150%-4 - -1
0100%0
540%1 - 5
10030%6 - 100

 

If the delivery of the items is three days early, the rating that is assigned to the delivery is 50%.

If the delivery is four days late, the rating assigned to the delivery is 40%.

 

Change Unit to Days
Changes the time unit from Hours into Days.
Change Unit to Hours
Changes the time unit from Days into Hours.