Operation storage horizon

To define a resource 's operation storage horizon, use the Operations Storage Horizon field in the Maintain Resource Master Plan (cprpd2100m000) session.

A resource's operation storage horizon is the number of future working days for which LN stores the operations for planned orders.

For planned orders beyond the operation storage horizon, you cannot analyze the capacity use of planned orders, and you cannot transfer the planned orders to the execution level.

The operations storage horizon must be at least as long as the longest of the time fences of the plan items produced at the involved resource.

A larger value of the operation storage horizon increases the data growth.

Recommendation:

  • Do not make the number of days in the Operations Storage Horizon field too large.
Performance aspects
  • Effect on CPU: Not applicable
  • Effect on database growth: Yes