Project Planning

This topic describes the differences between the Project Planning module in Infor LN SP1 and in Infor LN FP2 that are not already discussed in other Differences topics.

New and changed functionality

  • The Activity Relationship checkbox has been added to the following sessions to enable copying and/or deletion of the relationship data:
    • tppss0210m000
    • tppss0211m000
    • tppss2200m000
    • tppss2201m000
    • tppss2204m000
  • The Ownership Activity Relationships field has been added to the External Schedule Links (tppss2130s000) session which enables you to specify the ownership of the activity relationship.
  • The default Number Group and Series and the default Lead/Lag time unit for the activity/budget relationship are defined in the PSS Parameters (tppss0100s000) session.
  • The Order Priority field has been added to the Planned PRP Warehouse Order (tppss6115s000) session to enable better priority calculation.