Critical Capacity Requirements (cprmp3560m000)

Use this session to list the plan items for which a particular resource forms a critical capacity requirement.

On the View menu, you can select three different view modes to display critical capacity data:

  • Scenario, Work Center, Req. Period, Plan Item, Org. Period: LN displays the plan item for which the capacity of the specified resource is required in the period specified in the Period Required field.
  • Scenario, Plan Item, Org. Period, Work Center, Req. Period: LN gives an overview of all the resource capacities required for a certain plan item with the periods in which they are required.
  • Scenario, Plan Item, Req. Period, Work Center, Req. Period: LN gives an overview of all critical capacities required for the specified plan item in a certain plan period.

The origins of critical capacity requirements are listed for a specific combination of the following:

  • Scenario.
  • Resource.
  • Plan period, that is, the plan period in which the capacity is required, or the plan period in which the requirement for a specific plan item falls.

You can use the commands on the appropriate menu to further analyze the critical capacity requirements that LN displays in this session.

Note

If you started this session by zooming, you can only find and select a record.

 

Scenario
The scenario for which LN displays the critical capacity requirements for the specified resource.
Resource
The resource of which capacity is required to produce a certain plan item.
Period Required
The plan period in which critical capacity is required to produce the plan item (specified in the Plan Item field).
Plan Item
The plan item for which capacity is required at the specified resource.
Originating Period
The plan period in which the planned receipt of the manufactured item, specified in the Plan Item field, falls.
Capacity Required
The resource capacity (in hours) that is required to produce the specified plan item.