RRP run, Parallel ProcessingIn an order-based planning run in the Generate Order Planning (cprrp1210m000) session, you can optionally use parallel processing. In this case, LN uses multiple, parallel bshells to carry out the planning calculations. The planning of items with the same phase number is distributed over the parallel bshells (in batches of 25 items). Setup The following setup is recommended:
Select the Parallel Processing check box in the Generate Order Planning (cprrp1210m000) session to use parallel processing. The first time that you do this, a new record is inserted in the Performance Boosters (tcmcs0597m000) session. In the in the Value field in the Performance Boosters (tcmcs0197s000) detail session, you can specify the number of servers (that is, the number of parallel processes). The default value is 5.
| |||