| Service order processingService orders are generated from the Call Management module, Service Planning & Concepts module, and Infor LN Project. However, you can also create service
orders manually. If required, you can create the service order from a
quotation. Another way to create a service order is to generate orders out of
the FCO functionality. Service orders can be defined and processed on active
PCS projects, or on already delivered PCS projects. The service order can have several statuses throughout the order
life cycle, ranging from Free to Closed. These statuses enable you to control the service
order. Interruption is a sub-status that you can use for parts non-availability
or because the customer’s asset is not available or any other
reason. The following statuses are available with the following
meaning: Free The order is currently not planned or scheduled. Everything
can be changed. Planned The Planned status is to enable service resource planning
(SRP) to plan the order, which means that the parts required will be allocated
to the warehouse or purchased. The activities are soft allocated to the
preferred service engineers for a configuration. Released When the order reaches this status, the order is ready to be
executed. If intelligent scheduling is required, this can be achieved by a
service scheduler or by a service scheduler assistant. Alternatively, if fixed
(preferred) engineers are allotted to service orders, a batch process can be
run to plainly release a service order. In any case, this step would release
warehouse material, if stock is available, and enables you to start execution
of the orders. Emergency calls can be transferred to service orders in Released
status directly. Completed The job is finished, material used, hours used, and so on, and
can be entered in LN. Costed All costs and expenses are booked to the service order, so the
auditor can check the order. Contractual obligations and warranty obligations
are checked to calculate the invoice price. This also means that costs are
properly booked and the invoices for these service orders can be
sent. Closed The invoice process is also carried out, which means that the
order is entirely processed and, therefore, can be closed and deleted. However,
before orders can be closed the reconciliation processes in Financials must be
carried out.
The steps to carry out also depend on the service procedures
that were selected. If, for example, the Preventive Maintenance for Plant
(Internal) Maintenance service procedure is selected, no invoice is created but
Service costs are booked. If a warranty is valid for an asset, either no invoice is made
or discounts are offered based on the agreements, but possibly a more detailed
report about the problem will be required from the engineer. Repair warranty
can be made applicable based on the company policies or based on a selection by
you by means of a Service type. Repair warranty offers 100 percent
coverage. | |