To recalculate amounts of planned maintenanceYou can recalculate the cost amounts for a planned activity in the Planned Activity - Costs Overview (tsspc2513m000) session. Three situations are possible:
The cost type is used for the Material values, Labor, and Other. If a requirement line is added, deleted, or modified, LN calculates and updates the amounts for the related activity and the related Installation groups and serialized items. If an activity is added or deleted to an Installation group, LN recalculates and updates the amounts of that Installation group and the possible related serialized items. If the Item field is changed for a planned activity, LN updates the amounts of that serialized item and the related Installation group. If you choose Recalculate Amounts on the appropriate menu, all records of this table are updated (when applicable). The cost changes in the following sessions affect the cost amounts:
| |||