To recalculate amounts of maintenance concepts

You can recalculate the cost amounts for a maintenance concept in the Reference Activity - Costs Overview (tsacm2525m000) session. There are two possible situations:

  • The amounts are stored by reference activity. The Cost Type and the Cost Amount fields must be entered.
  • The Reference Activity and Cost Type fields must be entered.

The cost type is used for the material costs, labor costs, and other costs values. If a requirement line is added, deleted, or modified, LN recalculates and updates the amounts for the related activity and the related maintenance concepts. If a reference activity is added to or deleted from a maintenance concept, LN recalculates and updates the amounts of that concept.

A maintenance concept is identified by the Reference Activity field.

Cost changes in the following sessions affect the cost amounts:

  • Items - Costing (ticpr0107m000)
  • Labor Rate Codes (tcppl0190m000)
  • Tasks (tsmdm0115m000)
  • Service Departments (tsmdm1100m000)
  • Reference Activities (tsacm1101m000)
  • Reference Activity - Resource Requirements (tsacm2120m000)