To recalculate amounts of maintenance conceptsYou can recalculate the cost amounts for a maintenance concept in the Reference Activity - Costs Overview (tsacm2525m000) session. There are two possible situations:
The cost type is used for the material costs, labor costs, and other costs values. If a requirement line is added, deleted, or modified, LN recalculates and updates the amounts for the related activity and the related maintenance concepts. If a reference activity is added to or deleted from a maintenance concept, LN recalculates and updates the amounts of that concept. A maintenance concept is identified by the Reference Activity field. Cost changes in the following sessions affect the cost amounts:
| |||