Planned PRP Warehouse Order (tppss6115m000)

Use this session to maintain planned PRP warehouse orders for a project.

In this session you can:

  • Manually create PRP warehouse orders.
  • Modify existing PRP warehouse orders that were re-generated in the Generate Planned PRP Orders (tppss6200m000) session, or created in the current session.

If you create a new order, or modify the quantity of an existing order for materials taken from a normal warehouse, an inventory check is made according to the Check Inventory for Warehouse Deliveries setting in the PSS Parameters (tppss0500m000) session and the Negative Inventory Allowed parameter in the Inventory Handling Parameters (whinh0100m000) session.

An inventory commitment is made if the following is true:

  • The value of the Commit Inventory On field in the Project (tppdm6100m000) session is set to Insert.
  • There is sufficient stock in inventory.
Note

The order price determines the price for which the goods are received (ship-to).

In the following cases the order price will overrule the inventory valuation:

  • Delivery from a normal warehouse to a project (A)
  • Delivery from a normal warehouse to a project warehouse (B)
  • Delivery from a project warehouse to a normal warehouse (C)

In case A, the difference between inventory valuation and the order price is booked as project transfer result.

In cases B and C, the difference between inventory valuation and the order price is booked as transfer result.

If you have no inventory valuations when you ship from a project, the order price will determine the price for which the goods are received and the price for which the goods are issued. If issue and receipt price match, there is no result. This will apply in these cases:

  • Delivery from a project to a project warehouse (D)
  • Delivery from a project to a normal warehouse (E)
Note

To select multiple records, hold the CTRL key.

 

Project
The code that uniquely identifies the project to which the PRP warehouse order belongs.
Order/Set
The code that uniquely identifies the PRP order.
Warehouse Delivery Type
The direction of the warehouse transaction.
Planned Order
Material Order
Item in Project
The code that uniquely identifies the item.

Code segments

The code consists of a project code field and an item code field. If the first segment is filled, the item is a project-specific cost object. Otherwise, the item is a standard cost object.

There are five possible combinations in the two segments:

  • The first segment is clear; the second segment is filled with a standard cost object.
  • The first segment is the current project code (TP); the second segment is filled with a cost object.
  • The first segment is the PCS project's project code; the second segment is filled with the manufactured item, which is the top of the bill of material.
  • The first segment is empty; the second segment is filled with a manufactured item. This is the top of the bill of material, and it has the to-order order policy. The corresponding button is Configure.
  • The first segment is empty; the second segment is filled with a manufactured item with an to-order order policy. The corresponding button is Customize.

If the inventory unit of the item(s) matches the unit of the warehouse item, the item(s) can be transferred.

Effectivity Unit
The effectivity unit code for the item linked to the PRP warehouse order
Description
The description or name of the code.
Product Variant
The product variant is used to trace back the configuration of the generic item.
Product Variant
The unique identification of a product variant.
Quantity
The amount of the item ordered.
Note
  • Quantity cannot be negative.
  • It is rounded off, according to the rounding factor of its unit, defined in Units (tcmcs0101m000).
  • It can be changed by the minimum order quantity, specified in the Item - Ordering (tcibd2100s000) session.
  • It can be changed by the maximum order quantity, specified in the Item - Ordering (tcibd2100s000) session.
  • It can be changed by the order-quantity multiple, specified in the Item - Ordering (tcibd2100s000) session.
Quantity
The unit of measure for the cost object. This unit can affect how budget line quantities are calculated.
Project Warehouse
If the delivery type is Wrh->Proj, the value of this field is the project warehouse to which the materials are shipped (either independent or related to the project you are sending from). By default, this field is filled from the destination warehouse as defined in either the element/activity or the project ( LN takes the element or the activity, depending on the budget type project control). If the activity/element destination warehouse is empty, LN takes the project level.
  • If the delivery type is Proj->Wrh, the value of this field is the project warehouse that ships the materials.
  • If the delivery type is Wrh->Wrh, the value of this field is the project WIP warehouse that ships the materials.
Note

If you leave this field empty, the goods are shipped directly from the project.

Order Status
The current order's status.
Deliverable
If this check box is selected, the warehouse order applies to a project deliverable.

Project deliverables are created and maintained in the Planned Deliverables (tppdm7100m000) session.

Order Text
If this check box is selected, a text is present.
Cost Control
Element
The element to which this cost object belongs.
Activity
The activity to which the cost object belongs.
Extension
The extension to which the cost object belongs.
Cost Component
The code that uniquely identifies the cost component of the planned PRP warehouse order.
Dates / Warehouse
Dates
Planned Order Time
The planned date and time to order the warehouse order.

Click Calculate to calculate the planned warehouse order time from the planned warehouse delivery time. Transportation time is calculated between the normal warehouse address and the project address or the project warehouse address and the project address. LN calculates the transportation time with the distance table and the zip code of the Distance Table by ZIP Code/Postal Code (tccom4538m000) and the Distance Table by City (tccom4537m000) session.

Planned Delivery Time
The planned date and time to transfer inventories. LN computes the planned delivery date for the purchase order when it carries out the Generate Planned PRP Orders (tppss6200m000) session.
Transaction Time
The date is set at the latest change to the warehouse order.
Warehouse
Item in Warehousing
The code that uniquely identifies the code of an item of which inventory can be transferred to and from a project or project warehouse by using a transfer order.

Code segments

The code consists of a project code field and an item code field.

There are three possible combinations of segments:

  • The first segment is clear; the second segment is filled with a standard cost object
  • The first segment is the current project code (TP); the second segment is filled with a cost object
  • The first segment is the PCS project's project code; the second segment is filled with the manufactured item, which is the top of the bill of material.
Note

If the item is different from the item in Projects, the item is an alternative item and the planned warehouse order is generated for this item. You can view this item in the Order Line Balance (Material) (tppss6500m000) session.

Warehouse
Use Warehouse Order Price
If this check box is selected, the Order Price field displays the warehouse price.

If this check box is cleared, the inventory valuation price is used.

Order Price
An estimation of the price of the planned PRP warehouse order item in the selected warehouse.

On delivery, Warehousing determines a new final price to be used only in case of a return.

Currency
The currency in which the order price is expressed.
Order Priority
Specifies the priority for the project warehouse orders in Warehousing.
Lot Selection
Lot
A number of items produced and stored together that are identified by a (lot) code. Lots identify goods.
Serial Number
The unique identification of a single physical item. LN uses a mask to generate the serial number. The serial number can consist of multiple data segments that represent, for example, a date, model and color information, sequence number, and so on.

Serial numbers can be generated for items and for tools.

Delivery
To Project
Project
The project to which the items are transferred.
Plan
The plan to which the items are transferred.
Activity
The activity to which the items are transferred.
Element
The element to which the items are transferred.
Extension
The extension to which the items are transferred.
Cost Component
The cost component to which the items are transferred.
Ship-to Business Partner
The business partner to whom you ship the ordered goods.
Warehouse
The project WIP warehouse to which the items are transferred.
Delivery Terms
The agreements with the business partner, concerning the way the goods are delivered. Relevant information is printed on various order documents.
Point of Title Passage
The point at which the legal ownership changes. At this point, the risk passes from the seller to the buyer.

 

Configure
Configures a product variant of the coded item in the item-in-project field.

Directly after this configuration, a PCS project is created (from all items, bills of material, and routings, generated for the product variant).

Customize
Customizes the standard-to order item or the configured item.
Print Planned PRP Warehouse Orders
Starts the Print Planned PRP Warehouse Orders (tppss6415m000) session.
Approve Planned PRP Warehouse Orders
Starts the Approve Planned PRP Warehouse Orders (tppss6225m000) session.
Transfer Planned PRP Warehouse Orders
Starts the Transfer Planned PRP Warehouse Orders (tppss6235m000) session.
Change to Planned Purchase Order
Warehousing Orders
Starts the Warehousing Orders (whinh2100m000) session.
Planned PRP Purchase Orders
Starts the Planned PRP Purchase Orders (tppss6810m000) session.
Map/Session Options by User
View Map
Calculate
Calculates the planned order time from the planned delivery time minus the order lead-times defined in Procurement.
Calculate
Calculates the delivery time from the planned order time plus the lead time.
Requirements
Starts the Effectivity Unit (tcuef0102m000) session where you can select the requirement(s) defined for the effectivity unit.