Update Work Authorization Status of Elements/Activities (tppss2205m000)

Use this session to update the work authorization status of the specified elements/ activities.

Note

The project status must be Active and only activities under the leading plan are considered for the update process.

 

Project
The From and To fields define a range of: the projects.
Extension
The From and To fields define a range of: the extensions.
Elements
If this check box is selected, you can select the range of elements.
The From and To fields define a range of: elements
Subtree of Activity Structure
If this check box is selected, the status is updated for the specified subtree/sub-structure.
Top Activity
The code of the top node of the sub-structure or the sub tree.
Description
The description or name of the code.
New Status
The work authorization status of the element/activity.
Reason Code
The reason for holding the work execution of the element/activity. The field is enabled only when the New Status field is set to On Hold.
Description
The description or name of the code.
Update Mode
Select the update mode.

Allowed values

Update Mode

Process Report
If this check box is selected, Infor LN prints a process report. By default, the check box is not selected.
Error Report
If this check box is selected, Infor LN prints an error report. By default, the check box is selected. You can clear it if you want to.