The code that uniquely identifies the project that you want to
copy.
Copy Plans (tppss0211m000)Use this session to copy data from a project plan (the source) to a new plan for the same or another project (the target). The target project must not contain any data. Select the appropriate check boxes to copy activities, budget data and cost objects. Note
If the budget line with a PCS item is copied to another project, the PCS item cannot be copied and must be replaced:
Project The code that uniquely identifies the project that you want to
copy. Project A description of the project whose plans you want to copy. Project This status must be either free or active. Plan The code that uniquely identifies the plan you want to copy. Project The code that uniquely identifies the project you want the data to
be copied to. Project The project status must be either Free or Active. The copied
project has the status Free . So you can change the data if you want to. Plan The code that uniquely identifies the plan you want the data to be copied to. Copy Activities If this check box is selected, the activities are
copied. Copy Activity Relationships If this check box is selected, the activity relationship is copied. Note This check box is enabled only when the Copy Activities check box is selected. Copy Budget Lines If this check box is selected, the budget data is
copied. Note This check box is enabled only when the Copy Activities check box is selected. Source Version The current version of the time-phased budget. Use Already existing Cost Objects If this check box is selected, the cost objects that
already exist are copied. Conversion Factors The conversion factor for the item. Allowed values
| |||