The date for which the progress data must be generated.
Generate Physical Progress Master Data by Element/Activity (tpppc1110m000)Use this session to create master-progress data for elements and activities at the cost object level. You can only generate master data if both the project and the elements and/or the activities for that project meet the following conditions: Project conditions:
Element conditions:
Activity conditions:
Depending on the value of the fields, the progress is maintained at the level of cost object codes or cost control codes.
Physical Progress Date The date for which the progress data must be generated. Item If this check box is selected, LN generates progress data for the item cost
type. Labor If this check box is selected, LN generates progress data for the labor cost
type. Equipment If this check box is selected, LN generates progress data for the equipment
cost type. Subcontracting If this check box is selected, LN generates progress data for the
subcontracting cost type. Sundry Cost If this check box is selected, LN generates progress data for the sundry cost
cost type. Adopt Previous Figures If this check box is selected, the progress from the
previous Physical Progress Date is adopted by the newly
generated lines. New budget elements are generated with a zero line for
progress. If you did not enter progress yet for the given date, only the cost
object records and their quantities are inserted in the respective cost type
tables. Including Final Result If this check box is selected, master lines are
generated independently from the value of the Register Progress field for the project or the cost
object. Delete Existing Data If this check box is selected, the progress that is
newly generated for existing lines replaces the old generated control data
progress of these lines. If this check box is cleared, LN will put the lines that were deleted after generating control data back in the history when you generate progress here. Including Completed If this check box is selected, master data is generated
independently from the value of the Physical Progress Date field in the following
sessions.
| |||