Finish Variance

This bar metric displays the baseline finish date versus expected finish date. A positive difference between the expected finish date and the baseline finish date indicates an issue with the progress of the project. The project manager can investigate the issues and identify the reasons, based on which corrective actions can be initiated.

Infor LN selects the baseline finish date from the latest Approved Baseline details for the Top activity. The expected finish date is selected from the Project Scheduling Report. By default, the expected finish date is same as the baseline finish date of the top activity unless the user modifies the report.

[...]