| Ad hoc AnalysisThe Ad hoc analysis report allows you to review the expected,
actual and balance budget data for a specific project. Note To review these reports, adhering to the pre-defined sequence is
not mandatory. To generate the report: - Specify the data filters to generate a budget data report for
the specific project at specific level.
- Select the company. Click Company. The following pane is
displayed.
Select the options, similarly. - Select a method to calculate the actual cost.
- Review the budget data at the activity level.
- Click the arrow on the Activity field. The following pane is
displayed.
- Click Show top level elements to review the budget reports only
for the top activities.
- Click Level, to select the activity level at which the report
must be generated, using the following pane:
![[...]](../../images/level.png)
| |