Project Scheduling
Project Schedule status helps a project manager track the
project schedule and identify variances, if any, for the project. The Project
Scheduling report allows you to review the project performance with respect to
the schedule adherence.
The Project Scheduling report displays the following
data:
- Baseline: Approved project baseline.
- Base Line Start Date: Start date of the activity as defined in
the baseline.
- Base Line Finish Date: End date of the activity as defined in
the baseline.
- Actual Start Date: The date on which the activity
starts.
- Expected Finish Date: The date when the activity is expected to
be completed. This date can be different than the Base Line Finish
date.
- Actual Finish Date: The date on which the activity is
completed.
- Start Variance: The number of days by which the activity starts
prior to or later than the planned date. Start Variance = Baseline
Start Date - Actual Start Date
- Finish Variance: The number of days by which the activity is
expected to finish prior to or later than the planned date. Finish
Variance: Baseline Finish Date - Expected Finish Date
To generate the report:
- Specify the range of data for which you want to generate the
report.
- Review the schedule. Note: The Expected Finish Date can be specified
by the user.
- Review the graphical representation of the project schedule
performance using the Pie diagrams for the activities and milestones completed
/ yet to be completed.