Time Phased Project Performance
The Time Phased Project performance report allows you to review
the time phased budget and actual cost data for the current and the cumulative
period. Time phasing is based on the EV method defined for the
activity.
The various reports that can be generated:
- Time-phased budget vs Actual by Project
report
- Time-phased budget vs Actuals by Project / Activity
- Time Phased Budget Vs Actuals by Project / Activity / Cost
Component
- Time Phased Budget Vs Actuals by Project / Activity / Control
Code
To generate the report:
- Specify the range of data for which you want to generate the
report.
- Review the data.
- Click the project code in the Project field.
- Click Time Phased Budget Vs Actuals by Project / Activity to
view the report for time phased budget vs. actual cost for the current and
cumulative period, at the activity level.
- Review the time phased budget data for the current and
cumulative period at the activity level for the project.
- Click the activity code in the Activity field.
- Click Time Phased Budget Vs Actuals by Project / Activity /
Cost Component or the Time Phased Budget Vs Actuals by Project / Activity /
Control Code to view the report for the time phased budget vs. actual cost for
the current and the cumulative period, at the cost component or the control
code level.
- Review the time phased budget data at the cost component or
control code level for the activity, for the current and cumulative
period.