| Maintain EVM and Budget DataFollowing are the BI options you can use to view and maintain
the Earned Value Method and Budget data: - Maintain Earned Value Data
- Maintain Budget
- Maintain Schedule Version
- Generate Schedule by Project
Earned Value Management Earned Value Management (EVM) is the project management
methodology that integrates scope, schedule, and cost. The framework allows
project management professionals to monitor these three components. EVM
provides an objective measure of progress while delivering early warning
indicators through trends and estimates. You can maintain earned value methods for the following earned value types: - Earned value Start/End Percentage: Percentage values are
assigned to the start and end points of the activities. At the start of the
activity, a particular percentage of the project is completed and the budget
amounts are then released based on these percentages. :
Example: For an activity, the Scheduled Start
Date is 1st Jan 2012, Scheduled End Date is 20th March 2012 and the budget
amount is 10000 EUR. - Start Percentage = 70%
- End Percentage = 30%
- Time Phase Budget in Period 1 (Jan 12) = 10000 * 70% = 7000
EUR
- Time Phase Budget in Period 2 (Feb 12) = 10000 * 0 = 0
EUR
- Time Phase Budget in Period 3 (Mar 12) = 10000 * 30% = 3000
EUR
Note: You can
manually define the split percentage for the start and end of the
activities. - Earned value Percentage Complete : The budget amounts are
released in proportion to the progress percentage of the project. The budget
must be equally divided over the time period of activity start and end date.
Example: For an activity, the Scheduled Start
Date is 1st Jan 2012, Scheduled End Date is 20th March 2012 and the budget
amount is 10000 EUR. - Since the EVM is percentage complete, time phase the budget
proportionately over the duration of the activity.
- Activity Duration: 31 Days (in Jan) + 29 Days (in Feb) + 20
Days (in March) = 80 Days
- Time Phase Budget in Period 1 (Jan 12) = 10000 / 80 * 31 =
3875 EUR
- Time Phase Budget in Period 2 (Feb 12) = 10000 / 80 * 29 =
3625 EUR
- Time Phase Budget in Period 3 (Mar 12) = 10000 / 80 * 20 =
2500 EUR
- Earned value Milestones : Milestones are attached to the
activity and a percentage or amount of the budget is assigned to each
milestone. When a milestone is reached, the assigned budget is released.
Example: For an activity, the Scheduled Start
Date is 1st Jan 2012, Scheduled End Date is 20th March 2012 and the budget
amount is 10000 EUR. - The Activity is linked to Milestone M1 and M2.
- M1 (Scheduled Completion Date) = 12th Feb 2012
- M2 (Scheduled Completion Date) = 20th March 2012
- Percentage assigned to M1: = 40%
- Percentage assigned to M2: = 60%
- Time Phase Budget in Period 1 (Jan 12) = 0 = 0 EUR
- Time Phase Budget in Period 2 (Feb 12) = 4000 = 4000 EUR
- Time Phase Budget in Period 3 (Mar 12) = 6000 = 6000 EUR
Note: You can
manually enter or modify the percentages for each milestone.
| |