Disconnect project

Usually, you do not disconnect a project. If you work offline, you can simply synchronize when you are online again and update your project. The only reason to disconnect your project is if you discover that you linked to the wrong project, or if you decide to link to a different node of the LN project.

If you disconnect a project, the connection information stored in the External Schedule Links (tppss2130m000) session is deleted. On the budget lines, the link mode is also reset to No Link.

Note

To connect another Microsoft Project to the LN project, LN recommends that you reset the links on the budget lines to Create Link. You must reset these values line by line, or you can use the Global Update of Schedule Link (tpptc2202m000) session.