Save baseline

[...]

Save Baseline: This option is a feature of the integration application. The following are the two important points you must bear in mind:

  • You must have a synchronized structure/budget/schedule once you are sure that you can freeze the structure/budget/schedule with a baseline. The process is similar to running the Create/Update Baseline (tppss2220m000) session on the LN side, in which the user either creates a new baseline, possibly derived from an approved baseline, or updates an existing baseline.
  • The baseline plan must be the leading plan of the project.

The Save Baseline option includes the standard functionality of Microsoft Project, which enables you to save a baseline or an interim plan, extended with the possibility to save a baseline in LN Project, as in the Create/Update Baseline (tppss2220m000) session in LN.