| Save baselineSave Baseline: This option is a feature of
the integration application. The following are the two important points you
must bear in mind: - You must have a synchronized structure/budget/schedule once
you are sure that you can freeze the structure/budget/schedule with a baseline.
The process is similar to running the Create/Update Baseline (tppss2220m000) session on the LN side, in
which the user either creates a new baseline, possibly derived from an approved
baseline, or updates an existing baseline.
- The baseline plan must be the leading plan of the
project.
The Save Baseline option includes the standard
functionality of Microsoft Project, which enables you to save a baseline or an
interim plan, extended with the possibility to save a baseline in LN Project, as
in the Create/Update Baseline (tppss2220m000) session in LN. | |