Initial Project (PCS) Completion Date

  • Current Date

    The current date is set for completion of the PCS project.

  • Element/Activity Start Date

    The project completion date is based on the start date of the project element/activity.

  • Element/Activity Finish Date

    The project completion date is based on the finish date of the project element/activity.