Production Orders by Block (tisfc0152m000)Use this session to view and maintain the set of production orders that belong to a order block. You can use this session also to split an order block into two order blocks or remove a production order from an order block. After you deleted the last production order in an order block, LN deletes the order block automatically.
Machine The machine on which the order block's production orders are
produced. Start Date of Order Block Period The start date of the order-block period is the date that you
entered in the Start Date of Order Block Period field in the Generate Order Block Planning (tisfc0251m000) session. For more information, refer to the Help of the Start Date of Order Block Period field in the Generate Order Block Planning (tisfc0251m000) session. Block Sequence Number The value of the Block Sequence Number field determines the order in
which LN executes the order blocks. Together, the Machine field, Start Date of Order Block Period field, and the Block Sequence Number field uniquely identify an order block. Start Time The start time of the execution of this order block. More specific, the time when
this order block's machine starts work on the first production order of this
order block. End Time The end time of the execution of this order block. More specific, the time when
this order block's machine stops working on the last production order of this
order block. Original Planned Finish Date The original value of the relevant operation's planned finish date. At the time when LN retrieves an operation for a production order from the routing definition, LN also calculates the planned finish date. The Original Planned Finish Date field displays the original value of the Setup+Run (Next Oper.) field in the Production Planning (tisfc0110m000) session. For more information, refer to the Help of the Setup+Run (Next Oper.) or Requested Delivery Date field. Production Order An order to produce a specified quantity of an item on a
specified delivery date. Production Order Item The main item of the production order. Quantity Ordered The quantity to be produced by the production order. Inventory Unit The physical quantity in which an item or good is managed. For
example, a quantity of wood can be expressed as a length by using the unit of
one meter, or as a volume by using the unit of one cubic meter. Operation This operation's machine must be the machine of the order block. If the production order has more than one operation for the same machine, mixed with operations on other machines, the order-block functionality takes only the first of these operations into account. If the production order has multiple consecutive operations for the same machine, the order-block functionality uses the total of the run times of these operations. Operation Status The operation status. Current Setup + Run Start Date The date and time on which LN plans to start the production time. The Current Setup + Run Start Date field displays the current value of the Setup + Run field in the Production Planning (tisfc0110m000) session. The Current Setup + Run Start Date field does not reflect changes in the order blocks, until you update the standard production planning data. For more information, refer to the Help of the Setup+Run Start Date field. Current Wait Start Date The date and time on which the setup and run time of the
operation are planned to finish, and the wait time is planned to start. The Current Wait Start Date field displays the current value of the Wait field in the Production Planning (tisfc0110m000) session. The Current Wait Start Date field does not reflect changes in the order blocks, until you update the standard production planning data. For more information, refer to the Help of the Wait field in the Production Planning (tisfc0110m000) session, on the Planning Related tab, under Start Date.
Split Block Creates a new order block that contains all production orders
after the currently selected production order. The current order block retains
the range of production orders from the first production order through the
production order you selected. Split and Close Creates a new order block that contains all production orders
after the currently selected production order. The current order block retains
the range of production orders from the first production order through the
production order you selected. If no errors occurred, LN then closes the
session. Update Standard Planning Updates start times and end times displayed in the Production Planning (tisfc0110m000) session. Production Order Starts the Production Order (tisfc0101m100) session and displays the details of the selected
production order. Setup Classes and States Starts the Setup Classes and States by Operation (tisfc0133m000) session and displays the
operation's setup classes and setup states. Print Order Block Planning Starts the Print Order Block Planning (tisfc0451m000) session. Add Production Order to Order Block Starts the Add Production Order to Order Block (tisfc0252m000) session.
| |||