| Cost Price by Cost Type (tipcs3561s000)Use this session to display the total cost
price for a project per cost type as material costs, operation costs,
surcharges and general costs. Note LN displays the cost per cost type for
budgeted, estimated and actual costs. LN displays the cost price totals per cost
type. Project A collection of manufacturing and purchasing actions that are
performed especially for a particular customer order. A project is initiated by
a customer order for items having a To Order order policy. The purpose of a project is to plan and coordinate the production
of these items. For a standard-to-order production, the project is only
used to link the item with the customer order. Otherwise, a project can
include: - Customized item data (BOMs and routings)
- Project planning (activity planning)
A budget is a special type of project. A budget is used to
plan and estimate, not to carry out production. Currency The currency in which the costs
are expressed. Variable Estimated Amount The variable part of the estimated costs which have been posted
to the relevant cost price component, when the estimated cost price is being
calculated for the project. These costs are operation costs, material costs,
etc. Total Estimated Amount The total estimated costs which have been posted to the
relevant cost price component, when the estimated cost price is being
calculated for the project. These costs are operation costs, material costs,
etc. Total Actual Amount The total actual costs which have been posted to the relevant
cost price component, when the actual cost price is being calculated for the
project. These costs are operation costs, material costs, etc. Variable Budget Amount The variable part of the budgeted costs which have been posted
to the relevant cost price component, when the estimated cost price is being
calculated for the project. These costs are operation costs, material costs,
etc. Note During the cost
price calculation for the project, the budgeted costs are loaded directly from
the budget calculation! Total Budget Amount The total budgeted costs which have been posted to the relevant
cost price component, when the estimated cost price is being calculated for the
project. These costs are operation costs, material costs, etc. Note During the cost
price calculation for the project, the budgeted costs are loaded directly from
the budget calculation! | |