Cost Price by Cost Type (tipcs3561s000)

Use this session to display the total cost price for a project per cost type as material costs, operation costs, surcharges and general costs.

Note

LN displays the cost per cost type for budgeted, estimated and actual costs. LN displays the cost price totals per cost type.

 

Project
A collection of manufacturing and purchasing actions that are performed especially for a particular customer order. A project is initiated by a customer order for items having a To Order order policy. The purpose of a project is to plan and coordinate the production of these items.

For a standard-to-order production, the project is only used to link the item with the customer order. Otherwise, a project can include:

  • Customized item data (BOMs and routings)
  • Project planning (activity planning)

A budget is a special type of project. A budget is used to plan and estimate, not to carry out production.

Related topics

Currency
The currency in which the costs are expressed.
Variable Estimated Amount
The variable part of the estimated costs which have been posted to the relevant cost price component, when the estimated cost price is being calculated for the project. These costs are operation costs, material costs, etc.
Total Estimated Amount
The total estimated costs which have been posted to the relevant cost price component, when the estimated cost price is being calculated for the project. These costs are operation costs, material costs, etc.
Total Actual Amount
The total actual costs which have been posted to the relevant cost price component, when the actual cost price is being calculated for the project. These costs are operation costs, material costs, etc.
Variable Budget Amount
The variable part of the budgeted costs which have been posted to the relevant cost price component, when the estimated cost price is being calculated for the project. These costs are operation costs, material costs, etc.
Note

During the cost price calculation for the project, the budgeted costs are loaded directly from the budget calculation!

Total Budget Amount
The total budgeted costs which have been posted to the relevant cost price component, when the estimated cost price is being calculated for the project. These costs are operation costs, material costs, etc.
Note

During the cost price calculation for the project, the budgeted costs are loaded directly from the budget calculation!