| Generating Network MessagesFor each activity LN carries out the following
checks: - If the project is a subproject, LN checks that the
earliest start date of an activity is not before the start date of the
subproject.
- The desired start date
for an activity must lie between the earliest and latest start date.
- On the basis of the
progress of the preceding activities, LN checks whether the activity can start.
During this process, it signals whether the previous activities are before or
behind schedule.
- LN checks that the actual start date does not
lie before the earliest (computed) start date or after the latest planned start
date of the activity.
- If the project is a
subproject, LN checks
that the earliest finish date of an activity does not lie AFTER the completion
date of the subproject.
- The desired finish date
for an activity must lie between the earliest and latest finish
date.
- LN checks that the computed finish date of the
activity does not lie AFTER the latest planned finish date.
- LN checks that the actual finish date does not
lie before the earliest (computed) finish date or after the latest planned
finish date of the activity.
LN reports any deviations between the project's
planned and actual progress, or inconsistencies in the network
planning. | |