| Aggregating Estimated Capacity to ProjectDependent on the value of the Critical Capacity for Planning field in the Work Centers (tirou0101m000) session, Man Capacity or Machine Capacity is used to calculate the aggregated capacity. You can decide to link activities to the customized
operations during the aggregation process. This goes as follows: - If the activity code in
the Activities (tipcs4101m000) session has not been filled in, or if you indicated
that the code can be overwritten, LN first searches for an activity in which the
task AND the work center of the activity match the task
and the work center of the customized operation.
- If this activity code is
not present, LN searches
for an activity in which the task OR the work center of
the activity matches with the task or work center of the customized
operation.
- If this activity code is
not present, LN searches
for an activity in which the main work center of the activity matches the main
work center of the customized operation.
- LN, finally, reports if the customized
operation cannot be linked to an activity.
| |