| Closing a projectBefore a project is
closed, LN checks the
current status of the project. Only projects with the status Finished can be closed. LN checks that: - All subprojects have the
status Closed, if there is a main
project.
- All production orders
for the project are closed.
- All purchase orders have
the status Closed.
- All purchase receipts
are invoiced, and the invoice matching procedure are carried out in the
financial accounting.
- All sales orders are
closed with the Process Delivered Sales Orders (tdsls4223m000) session.
- All service orders for
the project are processed in history.
- All transaction hours
for the project are processed.
- No project inventory is
still present. The project inventory value cannot exceed the value entered by
the users. Remaining inventory less than this value is automatically
deleted.
- All internal invoices from the PCS project to the financial
companies of the sales office, service department, and/or warehouse are sent
and completed.
If these conditions are
not met, the project cannot be closed. If the project can be closed, the
following steps are taken: - Any current inbound and
outbound advice for warehousing orders in the Inventory by Warehouse, Item and Effectivity Unit (whwmd2116s000) session is
deleted.
- Project costs and
results are calculated. To do this, LN automatically starts the Calculate Cost Prices by Project (tipcs3250m000) session.
- The project status is
changed to Closed.
Note - If there is a main project, before the main project is
closed, all subprojects are closed first according to the previous
procedure.
- If you select the COGS and Revenues restricted to Financial Company of PCS Project check box in the Project Control Parameters (tipcs0100m000) session, financial transactions are posted
on the financial companies of the sales office, service department, and/or
warehouse instead of on the financial company of the PCS project. If internal
invoices are sent from the PCS project to those departments, and the internal
invoices are not completed yet, the Close Project (tipcs2250m000) session sets the project status to To be Closed instead of to Closed. You
must first complete the internal invoices, and then run the Close Project (tipcs2250m000) session again to set the project status to Closed.
| |