| Adding Production Order To Order BlockIf you enter values in the fields of this session, and click Add Order to Production Order Group, LN performs the
following actions: Checks whether Order Block Planning (tisfc0151m000) session already has records for the specified machine and the specified start date of order-block
period. If no such order blocks exist, this session cannot add
production orders to order blocks. - Determines which of the production order's operations is executed on the machine
that you specified. If multiple operations are executed on the same machine, LN selects the first of
these operations.
For each of the setup classes you specified in this session, LN searches the
applicable setup state, as defined in the Setup Classes and States by Operation (tisfc0133m000) session. If LN finds no such setup state for the operation, LN assumes that the
operation has the setup state that comes after all other setup
states. - LN checks the Order Block Planning (tisfc0151m000) session for order blocks with the same
set of setup classes and setup states as the production order that you want to
add.
- If LN finds such an order block, LN checks whether that order block's start date is on or after the
value of the Add to Block Planning After field.
If LN found an order block that meets these criteria, LN adds the production
order to the order block. If LN found no suitable order block, LN inserts a new order
block in the Order Block Planning (tisfc0151m000) session, and adds the production order
to the new order block.
After you added production orders to an order block, or removed
production orders from an order block, you must reschedule the order
block. To reschedule an order block, in the Order Block Planning (tisfc0151m000), on the Specific menu, click Reschedule Order Blocks. | |