| Calculating Assembly Part RequirementsThe assembly part requirements are calculated for product variants that meet
the following criteria: Note - If you enter a Date outside the demand time fence, a warning message
appears.
- Product variants that fall within de demand time fence can
also fall within the allocation time fence. In that case the assembly parts are
likely to be already allocated by Assembly Control, that is, by the Build Assembly Part Allocation (tiasc7240m000) session. If the parts are not allocated, or
if not all parts are allocated, the assembly lines for which the parts are not
allocated, are taken into account by the current session. Refer to the Product Variant - Assembly Lines (tiapl3520m000) session for the allocation status by
assembly line.
- Assembly parts for which the Floor Stock check box is selected in the Flattened Assembly Parts and Operations (tiapl2520m000) session are not taken into
account by the current session.
- The current session calculates the assembly part requirements
based on segment schedules, which is a rough calculation useful for high
volumes. The segment schedules appear in the Segment Schedules (tiapl4500m000) session.
- As opposed to the assembly part allocation that is carried
out in Assembly Control,
the current session calculates the requirements for all companies and assembly
lines in the selection simultaneously.
To ensure that the assembly part requirements are calculated
according to the latest data, the current session first performs the following
actions: - Update segment schedules. The segment schedules are
updated if changes are detected that affect the schedule, or if you selected
the Update Segment Schedules check box.
- Update allocation status. The allocation status is read from Assembly Control and
copied to Assembly Planning. The allocation status appears in Assembly Planning in the Product Variant - Assembly Lines (tiapl3520m000) session and the details of the Product Variants (tiapl3500m000) session.
- Generate product variant structures of the product
variants that meet the selection criteria described previously. After the
product variant structure is created, the Product Variant Structure generated check box is selected
in the details of the Product Variants (tiapl3500m000) session. Note that the product variant structure is
only generated if the External Product Variant Structure check box is cleared
in the Assembly Planning Parameters (tiapl0100s000) sesssion.
After these preparation steps, the assembly parts requirements
are calculated for the selected product variants, and the requirements are
transferred to Assembly Planning for all the related companies. The
requirements are transferred, using files that store the requirements by
company by date. The directory to which these files are written, is set in the Assembly Parts Requirements Directory field in the
details of the Assembly Planning Parameters (tiapl0100s000) session. After the assembly part requirements are calculated and
transferred, a completion report is created. If errors occurred, the Show Messages button is enabled. Click this button
to display the error messages. | |