| Purging and Renumbering SequencesYou can remove assembly orders if the following conditions are
met: - The status of the orders
is Closed.
- Their planned offline
date is before the date in the Upto Date field.
- The Assembly Order
Status in Line Sequence, that is, the status of the assembly order on a line
segment, of all orders that occur in the sequence of this assembly order must
be Completed. You can view the status of the orders in the Status field of the Assembly Line - Assembly Order Status (tiasl6501m000) session.
If an assembly order also appears in the supply lines, the
sequence in the supply line segments is also purged. If you select the Renumber check box, the following things
happen: - The position of the
order in the line sequence is changed.
- The assembly orders are
synchronized in all the supply line segments.
- The position numbers in
the line sequence are renumbered.
| |