Assigning Shared Work Center RelationshipsYou must already have defined the work centers as a shared work center in the Work Centers (tirou0101m000) session. When you create the relationship, the data about the primary work center is copied to the secondary work center. As a result, you can no longer edit the secondary work center data in the Work Centers (tirou0101m000) session, except for its description, the shop floor warehouse and backflush employee. Note The total percentage of the primary work center's capacity that is allocated to various secondary work centers, can be more than 100% to allow for overtime and other factors. As a rule, you must make sure that this value is less than or equal to 100%.
| |||