Effective Assembly Line Surcharge (ticpr3150m000)Use this session to display the item surcharges by assembly line that are effective when calculating the assembly costs. The effective assembly line surcharges are displayed in this session after running the Actualize Assembly Line Surcharges (ticpr2280m000) session. In the Effective Date field the date is displayed on which the assembly line surcharges are actualized. Surcharges are extra costs in an item's standard cost price or valuation price, for example, handling costs or inspection costs. A surcharge serves as a discount if the amount or percentage entered is a negative value.
Assembly Line A set of consecutive line stations in which FAS (Final Assembly
Schedule) items are manufactured. The items are manufactured by passing the
items from line station to line station and by carrying out operations at each
line station. An assembly line is subdivided into a number of line segments
separated by buffers. An assembly line can be either a main line or a supplying
line. Generic Item The generic item or manufactured item for which the Default Supply Source is Assembly. Effective Date The date and time on which the assembly line surcharges were
actualized in the Actualize Assembly Line Surcharges (ticpr2280m000) session. Sequence The number that identifies a data record or a step in a
sequence of activities. Sequence numbers are used in many contexts. Usually LN generates the
sequence number for the next item or step. Depending on the context, you can
overwrite this number. You can sometimes influence the numbering by setting the
corresponding parameters. Description The description of the assembly line's surcharge. Currency The currency in which the surcharge is expressed. Surcharge Method The method of calculating the surcharge for the assembly line. If the method is Selective (Total Costs) or Selective (Added Costs), a surcharge base is defined in the Assembly Line Surcharge Bases (ticpr1190m000) session to which the calculation applies. Allowed values Surcharge Amount The surcharge expressed as an amount. An amount is entered in
this field if the Surcharge Method field is Fixed Amount. Surcharge Percentage The surcharge expressed as a percentage. A surcharge percentage is entered in this field if the Surcharge Method field has one of the following values:
Cost Component The cost component to which the
assembly line's surcharge is linked. Variable Cost Surcharges can contribute to either fixed operation costs or
variable operation costs. Fixed operation costs are costs that are independent
on the number of items produced. Variable operation costs are costs that depend
on the number of items produced. In LN, cost prices and valuation prices can be
broken down into fixed costs and variable costs. If this check box is selected, the defined surcharge is considered as variable costs. A surcharge that is considered as variable costs will always be included in FTP inventory valuation. If this check box is cleared, the defined surcharge is considered as fixed costs. A surcharge that is considered as fixed costs, will only be included in FTP inventory valuation if the Include Fixed Costs in Valuation Price check box in the Cost Price Calculation Parameters (ticpr0100m000) session is selected. Note
Effective Assembly Line Surcharge Bases Click to start the Effective Assembly Line Surcharge Base (ticpr3160m000) session. Show Current Data Click to display only the cost components that are effective at
the latest calculation date. Show All Data Click to display all cost components, also the cost components
that are not effective.
| |||