| Function: Process Purchase SchedulesThe purchase schedule must be processed so that purchase
releases will be generated for communication to the supplier. Process: Process Purchase Schedule (code:
MPS12a) The objective of this process is to process the purchase
schedule data. The user can check the following data: - Create the purchase schedule: manually, by means of call off
(see process DPS016) or by means of Enterprise Planning.
- Generate the purchase release and manage the
release.
- Regenerate the schedule, in case data of the schedule has been
changed
- Approve the release lines
- Process and terminate the purchase schedule
- Remove the processed reference IDs
- Delete the purchase schedule and view the data in
history
Assumptions: - Applicable for all purchase schedules.
IT support: - LN Order Management, Purchase Control
| |