To set up data for subcontracting the manufacture of goods for material supplied

This functionality is specific for India.

Complete the following steps to set up data for subcontracting the manufacture of goods for material supplied:

  • Create required items
    • In the Items - General (tcibd0501m000) session, create a manufactured item, a purchase item and subassembly items.
    • In the Bill of Material (tibom1110m000) session, enter the created purchase item and required details to maintain the BOM data.
    • In the Items - Production (tiipd0101m000) session, Routing tab, select the Subcontracting with Material Flow checkbox.
    • In the Item - Routings (tirou1101m000) session, specify the routing sequence number, order quantity and other required details to maintain the routing data.
    • In the Routing Operations (tirou1102m000) session, specify the Task, Work Center, Machine, Cycle Time [Min], Average Setup Time, Subassembly and the Subassembly Warehouse for each of the operation lines.
    • In the Subcontracting Rates (ticpr1160m000) session, enter the required details, task and the subcontracting rate for the items sent. Link the subcontracted service item and attach the cost component.