| Subcontracting for manufacturing(Old flow)This functionality is specific for India. Complete the following steps to set up data for the production
order for subcontracting the manufacture of goods: Create required items - In the Items - General (tcibd0501m000) session, create a manufactured item, a purchase item
and subassembly items.
- In the Bill of Material (tibom1110m000) session, enter the created purchase item and required
details to maintain the BOM data.
- In the Item - Routings (tirou1101m000) session, specify the routing sequence number, order
quantity and other required details to maintain the routing data.
- In the Routing Operations (tirou1102m000) session, specify the Task, Work Center, Machine, Cycle Time [Min], Average Setup Time, Subassembly and the Subassembly Warehouse for each of the operation
lines.
- In the Operational tab, specify the sub-assembly and the
warehouse for each of the operation lines.
- In the Subcontracting Rates (ticpr1160m000) session, specify the task and the subcontracting
rate for the items sent. Link the subcontracted service item and attach the
cost component .
| |