| To process customs for project importsThis functionality is specific for India. Heavy custom duty is imposed on the machinery imported for
projects. To reduce the initial cost, concessions are provided on the duty
paid. To process custom duty for project imports, take the following
steps: Create a purchase order In the Purchase Orders (tdpur4100m000) session, create a purchase order for the imported
goods. Define terms of delivery In the Purchase Orders (tdpur4100m000) session, click the browse arrow of the Terms of Delivery field to select the terms of
delivery from the Delivery Terms (tcmcs0141m000) session. For details,
refer to INCO Terms. Maintain landed costs for purchase order In the Purchase Order Lines (tdpur4101m000) session, on the appropriate menu, click Landed Cost Lines; the Landed Cost Lines (tclct2100m000) session opens. Define the landed costs. Select aggregate tax code In the Purchase Order Lines (tdpur4101m000) session, select aggregate tax code from the Tax Codes by Country (tcmcs0536m000) session. Approve the purchase order In the Purchase Order Lines (tdpur4101m000) session, on the appropriate menu, click Approve. LN defaults
the order line in the Purchase Receipts (tdpur4106m000) session. Generate bills of entry In the Purchase Receipts (tdpur4106m000) session, on the appropriate menu, click Generate Bill Of Entry; the Bill of Entry (tdpur9140m00l) session opens. Enter the actual values in the Bill of
Entry and approve the receipt line. For details, refer To process bill of entry. Confirm Purchase receipts In the Purchase Receipts (tdpur4106m000) session, on the appropriate menu, click Confirm Receipt to confirm the receipt
line.
| |