Project pegging

Project pegging functionality can be implemented by selecting the appropriate parameters in these sessions:

  • Implemented Software Components (tccom0100s000)
  • Project Pegging Parameters (tcpeg0100m000)
  • Items - General (tcibd0501m000)
Example

If, in the Implemented Software Components (tccom0100s000) session, the Project Pegging check box is selected, the number of transactions registered in Project Cost History (tpppc2100m000) session increases. This results in additional database growth.

Performance aspects
  • Effect on CPU: Yes
  • Effect on database growth: Yes