The Planning module contains the scheduling information for
projects. You use this module to define project plans and the associated
activities and milestones.
The planning parameter plans cover the default project plan and details that relate
to the external scheduling package, including currency, time unit, and details
of code lengths.
Milestone
An activity of zero days that usually represents a
significant event in the project is called a milestone. In many cases, a milestone is the completion of a
phase for a major deliverable. Milestones can be used to trigger invoicing and
the calculation of earned value.
Activity relationships
An activity relationship indicates that a certain activity
(successor) cannot start or end until another activity (predecessor) starts or
ends. The activities must be sequenced accurately to provide realistic
schedules.
Project uses external scheduling packages, for example,
Microsoft Project to determine scheduling information of the activity
structure. You can use this scheduling information for an activity budget and a
time-phased budget.
External scheduling interface
Export a project to an external scheduling package such as
Microsoft Project by using an XML file. After you maintain the project plan in
the external scheduling package, you can import the updated scheduling
information to LN.