| Request for QuotationsWith the request for
quotation (RFQ) procedure, you can send RFQs to bidders for the procurement of
goods. On an RFQ, information regarding items, quantities, and required receipt
dates can be specified. The created RFQ can be sent to one or a range of
bidders based on the approved source list. After receipt of the RFQ responses,
the results can be negotiated and compared with objective and subjective
criteria based on which a purchasing decision can be made. An accepted RFQ can
be copied to a purchase contract, a purchase order, or a supplier price book. RFQs can be generated from planned orders, requisitions, or
purchase contracts. They can also be manually specified. The request for quotation (RFQ) procedure includes the creation and communication of the RFQs to the
appropriate bidders, and the receipt, negotiation, comparison, and selection of
the bidders' responses. If you sent RFQs to bidders, you can rank the responses that
you get back from the bidders to decide from which bidder you will purchase.
Before you can rank the responses, LN must calculate the scoring values for
each response. The procedure for calculating the total scoring value for each
criterion includes several steps. RFQ responses are ranked based on the total scoring values for
bidders. A number of processes do not always occur in the RFQ procedure,
but can be used optionally, such as printing RFQ reminders, printing letters
for unsuccessful bidders, viewing, printing, and deleting RFQ history. In case of operation subcontracting, requests for quotation
(RFQs) can include subcontracted service items. These RFQs can be manually
specified, or can be generated from a purchase requisition with a linked
routing operation or production order. To identify costs, demand, and supply for a project, you can
peg project costs for RFQ lines. Supplier stage payments enable customers to
pay suppliers before or after the ordered goods are actually received for a
purchase order. The payments are spread over a period of time and the amounts
must be paid to the supplier on specific dates. The purchase order item's
invoice flow is separated from its goods flow. On the RFQ response, you can
specify the stage payment lines, which can be copied to the purchase order line
during conversion.
| |