Copy Activities

Infor LN

In Infor LN, you could copy activities across plans, from a source structure to a target structure. If the target is the same plan you must define the source and the target. If the target is a different plan you define the source, select the Copy Across Plan check box in the Copy Activities (tppss2201m000) session and define the target.

Infor LN SP1

In Infor LN SP1, you can copy activities across projects. If the target is a different project, you must select the Copy Across Project check box in the Copy Activities (tppss2201m000) session and define the target project.

For more information refer to Copy Activities (tppss2201m000) session.