This topic describes the remaining differences between Infor LN 10.2.1 and Infor LN 10.3 in Warehouse Orders.
New and changed functionality
Temporary cost peg transfers
In Infor LN 10.3, borrow/ loan (temporary) cost peg transfer functionality is
implemented. LN allows
you to transfer the inventory from one project cost peg to another,
temporarily. In this scenario, inventory pegged to a specific project cost peg
is borrowed ( Borrow/ Loan - Payback) from one project cost
peg and used for another project cost peg during the warehouse outbound
procedure. The borrowed items must be replenished to the lending cost peg. This
is done using Payback and is generated on receipt of the inventory
actually ordered for the borrowing project cost peg.
In Infor LN 10.3, the shipping process involves Material Inspection and Receiving
report (DD Form 250). This requires acceptance of the goods by the customer.
These new sessions are added:
In Infor LN 10.3, the context application On Time Shipments (whinh8350m000) is added. Using this context application, you can view
the stacked bar chart with on time shipments, early shipments, and late
shipments for a specific warehouse over a specified period of time.
Completed shipments
In Infor LN 10.3, the context application Completed Shipments (whinh8351m000) is added. Using this context application, you can view
the stacked bar chart with completed shipments and unfinished shipments for a
specific warehouse for a specified date range.
Cycle counting variances
In Infor LN 10.3, the context application Cycle Counting Variances (whinh8352m000) is added. Using this context application, you
can view the bar chart with cycle counting variances by warehouse or by reason
for a specific warehouse for a specified date range.