Cost peg supplying relations

Cost peg supplying relations

In Infor LN 10.3, link cost pegs through a cost peg supplying relationship. You can transfer the project sub assemblies required for the project deliverables, through a warehouse transfer between business units implemented in different logistical companies. You can trace all costs for both the companies in comparison with another project. So, the multi-company warehouse transfer can have an outbound as well as an inbound cost peg.

To transfer the pegged items from the project:

  • The status of the receiving project must be Free or Active.
  • The Project Pegging check box must be selected in the Implemented Software Components (tccom0100s000) session for the receiving company.
  • The status of the supplying peg must be set to Free or Active.
Note
  • Infor LN allows you to link cost pegs only if the business units belong to different logistic companies.
  • Deliverables can be transferred between two projects, only if the receiving and supplying business units belong to different logistic companies.