Contract line links to project structure

Contract line links to project structure

In Infor LN you can link multiple contract lines (CLINs) to a project ( element structure/ activity structure). This enables you to track direct costs, compare revenues, and also estimate indirect costs, such as project management or testing, at the CLIN level. This functionality applies to all contract types, such as Fixed Price, Time & Materials and Cost Reimbursement.

Note
  • You can link a specific project peg (element/activity) to only one contract line.
  • You cannot link a project to multiple contract lines, if the contract types are different.

For more information, refer to Linking a CLIN to a project structure.