Lot Code Handling for Project Pegged Production Orders

In Infor LN 10.2.0 it was possible to have different lot codes for each distribution line. A new lot code could be generated for each distribution line or by effectivity unit as long as it was not reported complete.

In Infor LN 10.2.1 the effectivity unit for a project pegged production order is now zero or one.

Changes have been made:

Project Peg Priority during End Item Receipt or Material Issue
  • Infor LN 10.2.0

    In Infor LN 10.2.0 when distributing not the exact quantity but more or less than the full quantity of the material, the quantity is distributed over the distribution lines with project pegs in three steps:

    • When 'less than ordered' is handled, soft pegging data from Enterprise Planning is used to determine which supplies requirement date and requirement quantity is needed for each distribution line. Due to lot size rules, requirement quantity can be less than the ordered quantity. The distribution lines are handled in sequence or by requirement date.
    • If no soft pegging data is available or the complete required quantities from soft pegging data are fulfilled, the distribution lines are handled in descending sequence of the order quantity until the order quantity is fulfilled.
    • If the complete ordered quantities are fully fulfilled, the remaining quantity to fulfill is prorated over the distribution lines.
  • Infor LN 10.2.1

    In Infor LN 10.2.1 pegged demand lines are given priorities above unpegged demand lines during the first and second step.

    In case of step one when the requirement date is the same on a pegged and unpegged order and at step two when ordered quantities are the same.

Print order distribution when printing production order documents

A new field has been added to the Print Production Order Documents (tisfc0408m000) and Print Production Orders (tisfc0401m000) sessions: Order Distribution can now be printed as part of the production order documentation.

Copying order to Shop Floor Control with distribution