| Shop Floor ControlThis topic lists the differences for Shop Floor Control between Infor LN 10.2.0 and Infor LN 10.2.1. Lot Code Handling for Project Pegged Production
Orders In Infor LN 10.2.0 it was possible to have different lot codes for each
distribution line. A new lot code could be generated for each distribution line
or by effectivity unit as long as it was not reported
complete. In Infor LN 10.2.1 the effectivity unit for a project pegged production order is
now zero or one. Project Peg Priority during End Item Receipt or Material
Issue Infor LN 10.2.0 In Infor LN 10.2.0 when distributing not the exact quantity but more or less than
the full quantity of the material, the quantity is distributed over the
distribution lines with project pegs in three steps: - When 'less than ordered' is handled, soft pegging data
from Enterprise Planning is
used to determine which supplies requirement date and requirement quantity is
needed for each distribution line. Due to lot size rules, requirement quantity
can be less than the ordered quantity. The distribution lines are handled in
sequence or by requirement date.
- If no soft pegging data is available or the complete
required quantities from soft pegging data are fulfilled, the distribution
lines are handled in descending sequence of the order quantity until the order
quantity is fulfilled.
- If the complete ordered quantities are fully fulfilled,
the remaining quantity to fulfill is prorated over the distribution
lines.
Infor LN 10.2.1 In Infor LN 10.2.1 pegged demand lines are given priorities above unpegged demand
lines during the first and second step. In case of step one when the requirement date is the same
on a pegged and unpegged order and at step two when ordered quantities are the
same.
Print order distribution when printing production order
documents A new field has been added to the Print Production Order Documents (tisfc0408m000) and Print Production Orders (tisfc0401m000) sessions: Order Distribution can now be printed as part of the
production order documentation. Copying order to Shop Floor Control with
distribution If the main item copied to Shop Floor Control it is
now possible to copy the order distribution as well if the main item is
non-mandatory project pegged. | |