Miscellaneous differences

Project pegging on opportunities

In Infor LN 10.2.0, project pegging was introduced to identify costs, demand, and supply for a project. You can implement project pegging and specify the items for which project pegging is required. A peg is mandatory for an item only on the sales quotation line and sales order line.

In Infor LN 10.2.1, an item linked to an opportunity can also require a peg, which you can optionally specify in the Items by Opportunity (tdsmi1113m000) session.

In the Items by Opportunity (tdsmi1113m000) session, these project pegging-related fields were added:

When a sales quotation line is generated from the opportunity item line, the opportunity's peg is copied to the Budget, Element for Budget, and Activity for Budget fields on the quotation line.