| Order PlanningThe topic describes the differences between Infor LN 10 and Infor LN 10.2.1 for the Order Planning module. New and changed functionality The following changes were made to the Generate Order Planning (cprrp1210m000) session: Use Planning Group Selection was added to the
selection range. When this check box is selected, other selection options are
disabled. The company concept parameter Project Pegging has to be enabled to use Use Planning Group Selection. The option Update Pegging Relations is checked by default when
the planning group selection is set. This check box can be cleared
manully. Parallel processing is now possible when executing
top-down or bottom-up planning.
The following changes were made to the Planned Order Distribution (cprrp1105m000) session: A Requirement Date was added for the distribution
lines.This date must match the requirement date of the planned
order. These initially hidden fields have been
added: The Specification (cprrp0101s000) session can now be started for a selected order
line. The project peg fields are printed in the Print Planned Order Distribution (cprrp1405m000) session. To start the Top Demand Order References (cprrp0541m200) session, double-click the distribution line.
This is a satellite session of Planned Order Distribution (cprrp1105m000).
New sessions The following sessions were added: The Specification (cprrp0101s000) session shows the
contents of a single specification. Only the active specification parameter
fields are shown. This session is started from: - Item Order Plan (cprrp0520m000)
- Planned Order Distribution Line (cprrp1605m000)
- Planned Inventory Transactions (whinp1500m000)
The Next Level Requirements (cprrp0541m100) session shows the quantities and
requirement dates for transactions that are necessary for the start of the next
order. If multiple independent demand orders exist for the next level
requirement they are show. It is possible to zoom to the Top Demand Order References (cprrp0541m200) session by using the appropriate menu. The Top Demand Order References (cprrp0541m200) session shows independent demand orders
downstream from the marked supply order. This is a display only
session.
| |