Full supply time

New in Infor LN 10

In Infor LN 10, the full supply time is introduced. This full supply time is the total time required to obtain an item that is not forecasted. This time is used to calculate the full cumulative order lead time for an item, which includes the cumulative lead time of purchased parts. Full lead times are used for information purposes only.

Example

For item A, the supplier communicated a supply time of 50 days. This is in fact a reduced lead time and is only possible because a three year forecast is sent to the supplier for this item. If additional quantities are needed, which are not included in the forecast, the supplier needs the full supply time, which is 300 days.

New fields
FieldIn session
Use Full Supply TimePurchase Parameters (tdpur0100m000)
Full Supply TimeItems - Purchase Business Partner (tdipu0110m000) and Purchase Contract Line Logistic Data (tdpur3102m000)
Calculated Full Lead Time (Days)Items - Purchase Business Partner (tdipu0110m000) and Purchase Contract Line Logistic Data (tdpur3102m000)
Update Calculated Full Lead TimeUpdate Calculated Lead Time in Item - Purchase BP (tdipu0210m000)
Full Cumulative Order Lead TimeItems - Planning (cprpd1100m000)
Full Non-Critical COLTItems - Planning (cprpd1100m000)