Freight order date modification
This functionality enables you to modify the Planned Load Date and Planned Unload Date and Tolerance Dates
( Earliest Load Date and Earliest Unload Date; Latest Load Date and Latest Unload Date) for a single or a
range of freight orders/freight order lines.
Infor LN FP6
In Infor LN FP6:
- Tolerances (earliest/latest (un)load dates) are only available
on freight order header level.
- Freight order lines only contain the planned load date and
planned unload date originating from the order header. These dates cannot be
modified and remain as originally planned.
Infor LN 10
In Infor LN 10:
- Tolerances (earliest/latest (un)load dates) are also available
on freight order lines.
- The freight order line planned load date and planned unload
date can be modified.
- A new session Change Planned Load/Unload Date (fmfoc2201m000) is added.